PROJECT INFORMATION
212101-Methodist Charlton ED Relocation
PROJECT NAME:
PROJECT SECTOR:
healthcare
PROJECT BUDGET:
$6,400,000.00
PHOTO UPDATES:
REPORTING MONTH:
August 16, 2022
REPORTING PERSON:
Bhavik Mishra
Company:















212101-Methodist Charlton ED Relocation
3-story addition at Methodist Charlton Medical Center. Level 1 contains an enclosed parking garage and mechanical
Spaces, approximately 40,000 square feet. Level 2 contains a relocated and enlarged emergency department,
Approximately 40,000 square feet. Level 3 contains shell space for a future patient room floor, approximately 30,000
Square feet. The project also includes a remote plant (8,000 square feet)
Company:
PROJECT SECTOR:
healthcare
PROJECT BUDGET:
$6,400,000.00
OUR PORTION OF THE WORK:
$0.00
REPORTING MONTH:
August 16, 2022
REPORTING PERSON:
Bhavik Mishra
PHOTO UPDATES:















TEAM

Bhavik Mishra
Project Manager
SAFETY
Number of Accidents:
0
Number of Incidents:
2
Comments on Safety:
Cumulative Work Day - 273
Cumulative Man Hrs - 282,567
Days W/O incident - 116
QUALITY
Number of Inspections:
620
Number of Non-Compliant Items:
5
Comments on Quality:
All Hard lids are reframed as a result of inadequate coordination between the trade partners.
SCHEDULE
Is the Project On Schedule:
No
Project Milestones:
Note:- Overall the project is 35 days behind the schedule
Approaching Milestone
Certificate of Occupancy - 9/26/22
Owner Move-in Start - 10/19/22
100% THHS Inspection - 11/22/22
First Patient - 12/15/22
The Approaching milestone is not able to achieve because slider doors for exam rooms got delayed due to unavailability of material and supply chain issues.
###
Comments on Schedule:
DIVISION 03 – CONCRETE
• North canopy colored paving concrete installed
• ED north paving formwork and reinforcing installation in progress
• Wheatland signal dart stop foundation installation in progress
• Existing North main parking concrete saw cutting and fine grading
DIVISION 07 – ENVELOPE
• ED North Composite wood look panel (Geolam) started
• ED Glass Fiber Reinforced Concrete ongoing at Stair #2 pop-up and west
elevation
• ED North Level 3 scaffolding erection & Z-girl installation for Terra Cotta
• ED South canopy light fixture layout and framing in progress
DIVISION 09 – FINISHES
• ED Level 2, Area A & B millwork installation ongoing
• ED Level 2, Area B ceiling grid and hard lid framing in progress
• ED Level 1, Area A & B painting continues
• ED Level 2, Area A & B tile ongoing
• ED Level 2, drywall installation and close walls nearing completion
DIVISION 22 – PLUMBING
• ED Level 2, Area C in-wall rough-in complete
• ED Level 2 overhead domestic water insulation in progress
DIVISION 23 – HVAC
• Campus chilled water transfer complete
• ED and Remote Plant Air Conditioning-on preparation work complete
• ED Level 2 Area D ductwork and hydronic piping and insulation ongoing
• ED CT Chiller installed
DIVISION 26 – ELECTRICAL
• ED Level 2, Area C & D in-wall rough-in complete
• ED Level 2, Area C & D overhead layout and rough in for framing
• ED Level 2 wire pull and terminations continue overhead
• ED Level 2, Area A & B light fixture wiring in progress
DIVISION 31 – SITE
• Wheatland Signal existing utilities locate and layout continues
• ED garage ramp grading in progress
• ED site Zone 1 irrigation installation in progress
Approaching Milestone
Certificate of Occupancy - 9/26/22
Owner Move-in Start - 10/19/22
100% THHS Inspection - 11/22/22
First Patient - 12/15/22
The Approaching milestone is not able to achieve because slider doors for exam rooms got delayed due to unavailability of material and supply chain issues.
Note:- Overall the project is 35 days behind the schedule






Budget
Overall Construction Cost
$0.00
Original Contract Value
$0.00
Current Contract Value
$0.00
Contract Value Difference
$0.00
Pending Change Orders
$0.00
Original Fee
$0.00
Projected Fee
$0.00
Difference in Fee
$0.00
Collected Fee to Date
$0.00
General Conditions/Requirements
$0.00
Total Expenses
$0.00
Difference
$0.00
Monthly GC/GR Allowance
$0.00
Reporting Month Expenses
$0.00
Reporting Month Difference
$0.00
Total Revenue
$0.00
Anticipated Profit
$0.00
Actual Profit
$0.00
Comments on Cost: