PROJECT INFORMATION
212116-Old Parkland Demo
PROJECT NAME:
PROJECT SECTOR:
healthcare
PROJECT BUDGET:
$5,000,000.00
PHOTO UPDATES:
REPORTING MONTH:
September 8, 2022
REPORTING PERSON:
RG
Company:
212116-Old Parkland Demo
Demolition of the former Parkland Hospital complex was built between 1951 and 1989. Approx 1.5 million SF.
Company:
PROJECT SECTOR:
healthcare
PROJECT BUDGET:
$5,000,000.00
OUR PORTION OF THE WORK:
$5,000,000.00
REPORTING MONTH:
September 8, 2022
REPORTING PERSON:
RG
PHOTO UPDATES:
TEAM
Steven Hallman
PM5
SAFETY
Number of Accidents:
Number of Incidents:
Comments on Safety:
QUALITY
Number of Inspections:
Number of Non-Compliant Items:
Comments on Quality:
We are working on the GMP budget. Working miscellaneous make ready projects.
SCHEDULE
Is the Project On Schedule:
Yes, Project is ON TIME
Project Milestones:
###
Comments on Schedule:
We received bids for the demolition of the structure on 8-29-2022. Bid interviews are scheduled for Tuesday 9-13-2022. We are approx $10 million over our October 2021 budget based on market pricing. We will be submitting our GMP around 9-20-2022. This project may be put on hold pending Board Action in October.
Budget
Overall Construction Cost
$0.00
Original Contract Value
$5,000,000.00
Current Contract Value
$5,000,000.00
Contract Value Difference
$0.00
Pending Change Orders
$0.00
Original Fee
$0.00
Projected Fee
$0.00
Difference in Fee
$0.00
Collected Fee to Date
$0.00
General Conditions/Requirements
$0.00
Total Expenses
$0.00
Difference
$0.00
Monthly GC/GR Allowance
$-1.00
Reporting Month Expenses
$0.00
Reporting Month Difference
$-1.00
Total Revenue
$317,725.00
Anticipated Profit
$480,000.00
Actual Profit
$114,185.00
Comments on Cost:
Project still in Precon stage. Construction starts in Dec/Jan.
TRADE PARTNERS
Company
Monthly Rating
(1 being the worst, 5 being the best)
Comments
No data was found
CLIENTS
Company
Monthly Rating
Comments
Beck, SH
5