PROJECT INFORMATION

212103-MCED Precon
PROJECT NAME:

PROJECT SECTOR:

Healthcare
PROJECT BUDGET:
$54,025.00

PHOTO UPDATES:

REPORTING MONTH:

July 29, 2022

REPORTING PERSON:

RG

Company:

Copeland
212103-MCED Precon
Preconstruction for Methodist-Charlton
Company:
Copeland
PROJECT SECTOR:
Healthcare
PROJECT BUDGET:
$54,025.00
OUR PORTION OF THE WORK:
$54,025.00
REPORTING MONTH:
July 29, 2022
REPORTING PERSON:
RG
PHOTO UPDATES:
TEAM
No data was found

SAFETY

Number of Accidents:
0
Number of Incidents:
0
Comments on Safety:
Because this project is in Preconstruction, we have nothing to report on safety.

QUALITY

Number of Inspections:
0
Number of Non-Compliant Items:
0
Comments on Quality:

SCHEDULE

Is the Project On Schedule:
On Time
Project Milestones:
###
Comments on Schedule:
Pre Con services only

Budget

Overall Construction Cost
$0.00
Original Contract Value
$0.00
Current Contract Value
$54,025.00
Contract Value Difference
$54,025.00
Pending Change Orders
$0.00
Original Fee
$0.00
Projected Fee
$0.00
Difference in Fee
$0.00
Collected Fee to Date
$0.00
General Conditions/Requirements
$0.00
Total Expenses
$0.00
Difference
$0.00
Monthly GC/GR Allowance
$0.00
Reporting Month Expenses
$0.00
Reporting Month Difference
$0.00
Total Revenue
$0.00
Anticipated Profit
$0.00
Actual Profit
$0.00
Comments on Cost:
Precon services still pending payment from Beck. 08/15/22: This was billed at the beginning of Methodist when JH was on his component team. We have billed this, but they haven't paid it yet.