PROJECT INFORMATION

212101-MCMC ED Expansion-EJ Smith Self Performance
PROJECT NAME:

PROJECT SECTOR:

healthcare
PROJECT BUDGET:
$2,729,019.00

PHOTO UPDATES:

REPORTING MONTH:

September 9, 2022

REPORTING PERSON:

Ianlexis Figueroa

Company:

212101-MCMC ED Expansion-EJ Smith Self Performance
Methodist Health System build a new three-story addition to Methodist Charlton Medical Center. A new 40,000 square foot Emergency Department (ED) located at Wheatland Road and Bolton Boone Drive will almost double the size of the current ED and increase the number of beds from 45 to 70. The new ED will include more trauma rooms, expanded ambulance bays, and new imaging equipment that will allow patients to be scanned without being moved for testing. The construction include a New Helipad, retaining walls, paving, sidewalk, light pole, foundation slab. The project also includes a remote plant (8,000 square feet)
Company:
PROJECT SECTOR:
healthcare
PROJECT BUDGET:
$2,729,019.00
OUR PORTION OF THE WORK:
$3,139,018.00
REPORTING MONTH:
September 9, 2022
REPORTING PERSON:
Ianlexis Figueroa
PHOTO UPDATES:
TEAM
Ian Figuerora_Square
Ianlexis Figueroa
Project Manager
Rick Garcia_Square
Rick Garcia
Sr. Construction Manager
Tanmay Jadhav
Project Manager, PM1

SAFETY

Number of Accidents:
0
Number of Incidents:
2
Comments on Safety:

QUALITY

Number of Inspections:
Number of Non-Compliant Items:
Comments on Quality:

SCHEDULE

Is the Project On Schedule:
Yes, Project is ON TIME
Project Milestones:
We are on schedule, but everyone else is not on schedule. They're about a month and a half behind. We'll have to leave the jobsite and come back after they catch up.
###
Comments on Schedule:

Budget

Overall Construction Cost
$0.00
Original Contract Value
$1,679,780.00
Current Contract Value
$3,139,018.00
Contract Value Difference
$1,328,722.00
Pending Change Orders
$0.00
Original Fee
$0.00
Projected Fee
$0.00
Difference in Fee
$0.00
Collected Fee to Date
$0.00
General Conditions/Requirements
$2,598,937.47
Total Expenses
$2,569,802.29
Difference
$29,135.18
Monthly GC/GR Allowance
$0.00
Reporting Month Expenses
$0.00
Reporting Month Difference
$0.00
Total Revenue
$3,038,646.00
Anticipated Profit
$409,999.00
Actual Profit
$409,999.00
Comments on Cost:
9/9/22 RG - $100K left to bill on this project. Cost to complete estimated at $80K.

TRADE PARTNERS

Company
Monthly Rating

(1 being the worst, 5 being the best)

Comments
No data was found

CLIENTS

Company
Monthly Rating
Comments
No data was found