PROJECT INFORMATION
173893 – 3T 1st Floor SW Experience Space
PROJECT NAME:
PROJECT SECTOR:
higher_education
PROJECT BUDGET:
$88,000.00
PHOTO UPDATES:
REPORTING MONTH:
September 9, 2022
REPORTING PERSON:
Nishant Shah
Company:
173893 – 3T 1st Floor SW Experience Space
This project is about removal of the existing flooring and installation of the new flooring in the 3T 1st Floor SW experience store. The scope also includes replacement of the door to be ADA compliant and add motion tracking cameras to the store so that they can track the customers coming and record their experience with the space.
The space is leased by third party from ATT (Owner) and Beck Group are the contractors.
Company:
PROJECT SECTOR:
higher_education
PROJECT BUDGET:
$88,000.00
OUR PORTION OF THE WORK:
$88,000.00
REPORTING MONTH:
September 9, 2022
REPORTING PERSON:
Nishant Shah
PHOTO UPDATES:
TEAM
Nishant Shah
Project Manager
SAFETY
Number of Accidents:
0
Number of Incidents:
0
Comments on Safety:
9/9/22 NS - There is a safety meeting before start of projects. As there was a lot of moving around of equipment in this project, training was provided for moving and handling the equipment. Also, every personnel is needed to wear PPE kit and leather shoes are a must on the site.
There is no incident or accident on this project so far.
The space in the scope has number of equipment and experience stations which needs power and in order to move them around, special care was taken with the electric connections to the equipment. The people moving the equipment were trained prior and only after were allowed to work.
Everyone going to the site either being owner, contractor or subcontractor are required to wear PPE and leather shoes on site are a must.
QUALITY
Number of Inspections:
3
Number of Non-Compliant Items:
1
Comments on Quality:
Beck group has a quality plan unique to each project and is reviewed during the staff meeting.
SCHEDULE
Is the Project On Schedule:
Yes, Project is ON TIME
Project Milestones:
###
Comments on Schedule:
The schedule was prepared by me and reviewed with the supervisor before submitting it.
Budget
Overall Construction Cost
$0.00
Original Contract Value
$70,000.00
Current Contract Value
$88,000.00
Contract Value Difference
$18,000.00
Pending Change Orders
$0.00
Original Fee
$2,600.00
Projected Fee
$2,600.00
Difference in Fee
$0.00
Collected Fee to Date
$0.00
General Conditions/Requirements
$8,000.00
Total Expenses
$0.00
Difference
$8,000.00
Monthly GC/GR Allowance
$8,000.00
Reporting Month Expenses
$0.00
Reporting Month Difference
$8,000.00
Total Revenue
$0.00
Anticipated Profit
$2,500.00
Actual Profit
$0.00
Comments on Cost:
These are the numbers provided by my Supervisor here at Beck Group as, I don't have access to the project accounts yet.
TRADE PARTNERS
Company
Monthly Rating
(1 being the worst, 5 being the best)
Comments
M C Commercial
4
It does most of the flooring for The Beck Group depending on the availability.
Country Glass & Mirror Inc.
4
They did a lot of glazing work for The Beck Group at the ATT Discovery District
CLIENTS
Company
Monthly Rating
Comments
ATT - Global Real Estate
4